PRINT

Indonesia: Development of Pumped Storage Hydropower in Java Bali System (the Project)

SUMMARY

STATUS
Approved
MEMBER
Indonesia
SECTOR
Energy
E&S CATEGORY
Category A
PROJECT NUMBER
000512

FINANCING

APPROVED FUNDING
USD230 million
FINANCING TYPE
Sovereign

TIMELINE

CONCEPT REVIEW
July 28, 2021
FINANCING APPROVAL
April 13, 2022
LATEST FIELD VISIT
December 2022

OBJECTIVE

The objective is to support Indonesia’s energy transition and decarbonization goal by (i) developing the first large-scale pumped storage hydropower to improve power generation peaking and storage capacity of the Java-Bali grid and (ii) strengthening PLN’s capacity for hydropower development and management.

DESCRIPTION

The Project will support PLN’s development of the Upper Cisokan Pumped Storage (UCPS) Hydropower Plant, including its environmental and social impact management, implementation, and monitoring, as well as capacity building for PLN in hydropower project preparation and management. World Bank (WB) is the leading bank and will co-finance with AIIB.

The Project consists of three components:

Component 1 – development of the UCPS plant

Component 2 – environmental and social impact management for the UCPS plant

Component 3 – technical assistance and capacity building for PLN.

ENVIRONMENTAL AND SOCIAL INFORMATION

WB has categorized the environmental and social (ES) risks of this project as “High”, which is equivalent to Category A if AIIB’s Environmental and Social Policy (ESP) were applicable.

WB is a lead co-financier, and the Project’s ES risks and impacts have been assessed in accordance with WB’s Environmental and Social Framework (ESF). To ensure a harmonized approach to addressing the ES risks and impacts of the Project, and as permitted under AIIB’s ESP, WB ESF will apply to the Project in lieu of AIIB’s ESP. AIIB has reviewed WB ESF and is satisfied that: (a) it is consistent with AIIB’s Articles of Agreement and materially consistent with the provisions of AIIB’s ESP, including the Environmental and Social Exclusion List and the relevant Environmental and Social Standards; and (b) the monitoring procedures in place that are appropriate for the Project.

Potential environmental impacts of UCPS plant are wide ranging and significant. Permanent changes in hydrological regime & land use, dam safety risk, occupational & community health, and safety risks result in residual impacts which are long term, permanent and irreversible. The key impacts include (i) potential loss of habitats & loss of key species of conservation concern; (ii) temporary downstream river impacts (sediment discharge from construction affecting water quality & stream bed patterns); (iii) changes in hydrological regime in Cisokan River; (iv) long term changes to erosion & deposition patterns downstream Cisokan River due to reduced sediment load during operation; (v) construction work that will bring potentially significant negative impacts on communities (sediment runoff, fugitive dust, increased noise, increased traffic, pedestrian & road safety risks, and increased wastes from construction camps); and (vi) dam safety risks, property, and ecosystem services. Specific mitigation measures to manage these impacts (e.g., Biodiversity Management Plan and Integrated Water Catchment Management) have been prepared. They will require requisite expertise for proper implementation.

On the social aspects of the project, the Land Acquisition and Resettlement Action Plans (LARAP) have been implemented by PLN and supervised by WB. The total number of households affected by land acquisition is 2,063, including 765 households who were physically resettled. The compensation payment and the livelihood assistance activities were completed for the 98.65% of land. The review of implementation of the LARAP identifies pending tasks and issues to be addressed, the resolution of which will require more time for investigation, planning and consultation with communities and local administration and will be undertaken during project implementation as reflected in the Environment and Social Commitment Plan (ESCP). In addition, a Land Acquisition and Resettlement Framework (LARF) has been prepared to guide resettlement planning to address any unexpected additional land acquisition and resettlement needs, particularly during construction.

Stakeholder engagement for UCPS started in 2009 under the previous WB loan and continued at different stages of the Project in the past decade. In the preparation of the proposed Project, PLN carried out extensive stakeholder consultations to inform the public of the project planning status and collect their feedback for the updating and development of Project ES plans. PLN has developed a Stakeholder Engagement Plan (SEP), and two Grievance Redress Mechanisms: one for the Project and the other specifically for Project workers.

The ES documents in English and summary in Bahasa, as appropriate, have been disclosed by PLN on its website. These documents have also been disclosed on WB’s website, and AIIB’s website will include links to these disclosures.

PROJECT TEAM LEADER

Asian Infrastructure Investment Bank

Ziwei Liao

Senior Private Sector Operations Specialist

ziwei.liao@aiib.org

 

World Bank

Stephan Claude Frederic Garnier

Lead Energy Specialist

sgarnier@worldbank.org

BORROWER

Luky Alfirman

Director General of Budget Financing and Risk Management Ministry of Finance of the Republic of Indonesia

luky.alfirman@kemenkeu.go.id

IMPLEMENTING ENTITY

Evy Haryadi

Director of Corporate Planning

e.haryadi@pln.co.id

Home Projects Project Summary Project List Project Details Indonesia: Development of Pumped Storage Hydropower in Java Bali System (the Project)