To enhance all-weather connectivity between Phnom Penh and the Cambodia-Viet Nam border through the NR8 corridor.
The loan will support widening, upgrading, and climate-proofing of approximately 129.1 km of existing national roads (NRs) (123.6km of NR8 and 5.5 km of NR88) from Phnom Penh to the Cambodia-Viet Nam border, passing through three provinces – Kandal, Prey Veng, and Tboung Khmum. The loan includes construction and improvement of drainage infrastructure, as well as strengthening of bridges, box culverts, and pipe culverts. The loan will also support the strengthening of the project management capacity of the Project Management Unit (PMU), preparation of technical documents, and provision of construction supervision.
Applicable Policy and Categorization. AIIB’s Environmental and Social Policy (ESP), including the Environmental and Social Standards (ESSs) and the Environmental and Social Exclusion List (ESEL), will apply to this project. ESS1 (Environmental and Social Assessment and Management) and ESS2 (Land Acquisition and Involuntary Resettlement) are triggered. ESS3 (Indigenous Peoples) is not triggered as no presence of Indigenous People is identified by now. The project has been categorized as B because the works will largely follow the existing alignment and are expected to generate impacts that will be site-specific, temporary, largely reversible, and that can be managed using good practice in an operational setting.
Environmental and Social (E&S) Instruments. The implementing entity, the Ministry of Public Works and Transport (MPWT) will prepare, consult on, disclose and implement proposed E&S instruments acceptable to AIIB, including: (i) an Environment and Social Impact Assessment (ESIA); (ii) an Environmental and Social Management Plan (ESMP) specifying mitigation, monitoring, responsibilities, budget, schedule and contractor obligations; (iii) a Resettlement Planning Framework (RPF) and Resettlement Plans (RPs), when detailed engineering designs become available; (iv) a Stakeholder Engagement Plan (SEP); (v) Labor Management Procedures (LMPs); and (vi) construction and operational traffic and road safety plans.
E&S Aspects. No major biodiversity impacts are expected. Implementation phase impacts may include noise generation and air emissions from construction activities. Contamination of surface water and groundwater from construction activities and inappropriate discharge of domestic wastewater may lead to water quality impacts. Solid and hazardous waste generation is similarly expected due to the use of hazardous materials, such as fuel and oil. These potential risks and impacts are short-term, and low in magnitude, and will be mitigated through the measures proposed in the ESMP. The implementation of the project may impact on small structures, roadside businesses, vendors, crops, trees, access arrangements, public structures, and livelihood activities. Potential land acquisition and involuntary resettlement risks were also identified, including 4,421 affected households, and 18,293 affected persons. However, the acquisition of private land outside the existing right-of-way (ROW) does not seem needed, as the affected land area is within the ROW. The identified social impacts are therefore expected to be largely localized, predictable, and manageable, which will be confirmed during appraisal based on the final corridor of impact, detailed measurement survey, cadastral and tenure verification, and updated socioeconomic assessment. Indigenous Peoples were not identified among affected households, which will be reconfirmed during appraisal. In addition, E&S instruments should also assess differentiated impacts on women and socially vulnerable groups. A gender equality and social inclusion (GESI) assessment and GESI Plan (GESIP) are being prepared by the PMU.
Occupational Health and Safety (OHS), Labor and Employment Conditions. Roadworks pose OHS and labor risks from traffic, heavy equipment, excavation, heights, electricity, dust, noise, vibration, heat stress, camps and possible unexploded ordnance (UXO) in earthwork areas. The PMU will prepare Labor Management Plans (LMPs) and require contractor site specific OHS and traffic plans, emergency procedures, camp management, codes of conduct and a confidential worker grievance mechanism. Gender-based violence (GBV)/sexual exploitation and abuse (SEA)/sexual harassment (SH) prevention and response measures should be integrated into contractor obligations and community interaction protocols.
Stakeholder Engagement, Consultation and Information Disclosure. The SEP will cover affected households, roadside businesses/vendors, farmers, women, vulnerable households, communities, commune/provincial authorities, road users, transport operators, border agencies, civil society, contractors and relevant ministries. Consultations will begin early in preparation and continue through implementation of the project. The ESIA, ESMP, RPF, SEP, GESIP should be disclosed by MPWT and the Bank in English and Khmer in accordance with ESP requirements.
Project Grievance Redress Mechanism (GRM). MPWT maintains several channels for the public to submit feedback, complaints, and service-related concerns. In addition, the PMU will also establish a project-level GRM before loan approval and maintain it throughout project implementation. The mechanism will provide accessible channels and clear procedures for receiving and resolving grievances at village, commune, provincial, and PMU levels. Contractors will establish a mechanism for workers and support grievance intake, resolution, and reporting as part of E&S monitoring. The information about the established GRMs and Bank’s Project-affected People’s Mechanism (PPM) will be disclosed in a timely and appropriate manner.
Monitoring and Reporting Arrangement. The PMU under MPWT will be responsible for implementing the project and conduct monitoring of the E&S assessment and management. The Bank will undertake semi-annual review missions to supervise the implementation progress of E&S instruments. Semi-annual E&S monitoring reports will be prepared by the PMU based on an agreed format and shared with AIIB for review.
Asian Infrastructure Investment Bank
Tomás Herrero Diez
Senior Investment Officer
Kingdom of Cambodia
Pen Thirong
Under Secretary of State, Ministry of Economy and Finance
Ministry of Public Works and Transport
H.E. Chhoun Vin
Secretary of State, Ministry of Public Works and Transport