PRINT

Nepal: Tamakoshi V Hydroelectric Project (TV-HEP)

SUMMARY

STATUS
Proposed
MEMBER
Nepal
SECTOR
Energy
E&S CATEGORY
Category A
PROJECT NUMBER
000261

FINANCING

PROPOSED FUNDING AMOUNT
USD112 million
FINANCING TYPE
Sovereign

TIMELINE

CONCEPT REVIEW
December 18, 2018

OBJECTIVE

The objective is to reduce the supply and demand gap by providing additional power to the national grid. The Project would also help stabilize the grid by contributing to meeting the daily peak demand.

DESCRIPTION

The project comprises four components listed below.

Component One-Civil and Hydromechanical Works: comprising the construction of the project’s hydraulic structures, all of which will be underground, and the installation of hydromechanical equipment.

Component Two-Electromechanical, Transmission Line, and Infrastructure Works, comprising the installation of electromechanical equipment and the construction of a small loop of double-circuit lines to existing transmission lines, permanent and temporary workers’ camps and access roads within the project site.

Component Three-Implementation of Environmental and Social Management Plans (ESMPs): including activities for resettlement compensation and livelihood restoration, monitoring of the catchment in terms of flows, watershed and sediment for optimal operation of the Project and an early warning system for the communities.

Component Four-Construction Supervision, Implementation Support, Technical Assistance and Monitoring and Evaluation of the Project Impacts and ESMP: The GoN has requested  a grant from the Bank’s Project Preparation Special Fund (PSF) to support the additional preparation required by the Bank’s policies, including additional technical reviews and environmental and social studies. These activities will be implemented by the NEA.

PROJECT FINANCING

For more information about project financing, please review the project summary.

ENVIRONMENTAL AND SOCIAL INFORMATION

The Project is subject to the Bank’s Environmental and Social Policy (ESP) and all three Environmental and Social Standards (ESSs) are applicable: ESS 1 – Environmental and Social Assessment and Management; ESS 2 – Involuntary Resettlement; and ESS 3 – Indigenous Peoples. The Project has been classified as Category A. The Project is located within the Gaurishankar Conservation Area (GCA); however, the “Regulatory” Environmental Impact Assessment (EIA) of TV-HEP, approved by the Ministry of Environment in June 2016, concludes that the Project is “environmentally feasible and the identified impacts in physical, biological, socioeconomic and cultural environment are mostly ranked as low to moderate and these impacts could be managed to an acceptable level by applying proper preventive, mitigation and rehabilitation measures.” AIIB has determined that preparation of a Supplemental Environmental and Social Information Package will be necessary to fully understand the potential environmental and social risks and impacts of the Project and identify proposed measures for their management in a manner consistent with the ESP. Land acquisition is expected to be limited to 28.5 hectares for the construction of the Project structure and facilities. In total, 35 households with 177 persons are tentatively 3 estimated to be affected by land acquisition, mostly limited to economic displacement. Only two of these households are expected to be physically displaced to date. At the same time, since the basin is experiencing rapid hydropower development, with 586MW under construction in the GCA, including the UTKHEP (456MW), there could be significant cumulative impacts, resulting in complete conversion of the Tamakoshi aquatic ecosystem into modified habitat. During project preparation, the Supplemental Environmental and Social Information Package will be prepared to address information gaps identified during the Bank’s initial site visit (Sept. 2018). This will include, but not be limited to, an assessment of climate change risks, downstream impacts, and a cumulative impact assessment that will include both the UTKHEP and the proposed Project. Stand-alone documents will include an Environmental and Social Management Planning Framework (ESMPF), Biodiversity Action Plan (BAP), Land Acquisition and Livelihood Restoration Plan (LALRP), Stakeholder Engagement Plan including Grievance Redress Mechanism, and a Vulnerable Communities Development Plan (VCDP) that is informed by a Free, Prior, and Informed Consultation (FPICon) process. These studies will include, as appropriate, use of public disclosure and consultation processes to support their preparation. As per ESS 3, the Project will be required to undertake FPICon under the guidance of a qualified and experienced independent expert. FPICon is an enhanced consultation process that requires documentation of a mutually accepted process of consultation between the Project and the concerned Indigenous Peoples and evidence of Broad Community Support of these communities on the outcome of the negotiations. As the Project is on an international waterway, the Bank will conduct a review of the potential need for a riparian notification process, consistent with the provisions of the Operational Policy on International Relations. AIIB’s Policy on the Project-affected People’s Mechanism (PPM) is applicable. The Project-affected People’s Mechanism has been established by AIIB to provide an opportunity for an independent and impartial review of submissions from Projectaffected people who believe they have been or are likely to be adversely affected by AIIB’s failure to implement its ESP in situations when their concerns cannot be addressed satisfactorily through Project-level Grievance Redress Mechanisms or AIIB Management’s processes.

PROJECT TEAM LEADER

Pratyush Mishra

Investment Operations Specialist

pratyush.mishra@aiib.org

 

BORROWER

Dil Bahadur Chhetry

Under Secretary
Ministry of Finance
Government of Nepal

chhetrydb@mof.gov.np

IMPLEMENTING ENTITY

Nasib Man Pradhan

Project Manager, Tamakoshi V Hydroelectric Project NEA/Tamakoshi Jalvidjyut Company Limited

tamakoshi5@nea.org.np

Home Projects Project Summary Project List Project Details Nepal: Tamakoshi V Hydroelectric Project (TV-HEP)